This page outlines the typical timelines for common development and planning processes in the Town of Stanton. These estimates are provided to help applicants prepare and plan ahead. Actual review times may vary depending on project complexity, the completeness of application materials, and the timing of public meetings.
Common Processes & Estimated Timelines
1. Zoning Change Request
-
Pre-application meeting:
1–2 weeks before formal submission -
Application submission & staff review:
3–4 weeks -
Planning Commission hearing:
Next available monthly meeting -
Board of Mayor and Aldermen (BMA) readings:
2 consecutive monthly meetings - Total Estimated Time: 8–12 weeks
2. Site Plan Review
-
Pre-application meeting:
1 week before formal submission -
Application submission & staff review:
2–3 weeks -
Planning Commission approval:
Next available meeting -
Revisions (if required):
1–2 weeks - Total Estimated Time: 4–6 weeks
3. Subdivision Approval
-
Master Plan (Preliminary Plat) review:
3–4 weeks before Planning Commission -
Construction Plans Review:
2–4 weeks -
Subdivision Agreement / Bond:
2–4 weeks -
Final plat review and approval:
2–3 weeks -
Recording at County Register of Deeds:
Within 1 week of approval - Total Estimated Time: 8–12 weeks
4. Variance or Special Use Permit
-
Application submission:
3–4 weeks before Board of Zoning Appeals (BZA) meeting -
Staff review and public notice:
2–3 weeks -
BZA hearing and decision:
Next scheduled meeting - Total Estimated Time: 5–7 weeks
5. Annexation Request
-
Pre-application meeting:
1–2 weeks before formal submission -
Application submission & staff review:
3–4 weeks -
Planning Commission hearing:
Next available monthly meeting -
Board of Mayor and Aldermen (BMA) readings:
2 consecutive monthly meetings - Total Estimated Time: 8–12 weeks
Note: Timelines are estimates only. Projects that require state or federal permits (such as TDOT driveway approval or TDEC stormwater permits) may take longer. Providing complete and accurate applications can significantly reduce review times.